Purchasing a fired heater for a refinery or petrochemical project involves much more than requesting a price based on heating capacity. A successful procurement process begins with a clear technical specification, accurate process data, and a well-defined scope of supply.
For EPC contractors, refinery operators, and industrial equipment buyers, an incomplete fired heater RFQ (Request for Quotation) can result in inaccurate quotations, design revisions, delivery delays, and unexpected project costs.
Two fired heaters with the same nominal heat duty may have significantly different prices because of their operating conditions, tube materials, burner systems, inspection requirements, and included equipment.
This guide explains the 15 essential technical details every buyer should prepare before contacting a fired heater manufacturer. It also provides a practical RFQ checklist, identifies common purchasing mistakes, and explains how to compare quotations from different suppliers.
1. What Is a Fired Heater RFQ and Why Does It Matter?
A fired heater RFQ is a formal document used to communicate the technical and commercial requirements of an industrial heating project to potential equipment manufacturers.
It typically includes process operating conditions, equipment specifications, applicable standards, inspection requirements, documentation, and delivery expectations.
A detailed RFQ helps manufacturers understand the actual project requirements rather than making assumptions based on limited information.
For example, a buyer requesting a 10 MW fired heater without specifying the process fluid, operating pressure, fuel composition, or required outlet temperature may receive quotations based on different engineering assumptions.
These quotations cannot be compared reliably.
A well-prepared RFQ helps buyers:
Receive technically comparable quotations.
Reduce repeated communication during engineering.
Identify important equipment exclusions.
Evaluate manufacturing and inspection requirements.
Clarify project responsibilities before placing an order.
Reduce the risk of costly changes after contract award.
Procurement tip: The objective is not simply to obtain the lowest fired heater price. It is to obtain a technically suitable equipment proposal with a clearly defined scope and acceptable lifecycle cost.
2. Fired Heater RFQ Checklist: 15 Essential Technical Details
The following information should be included in an RFQ wherever applicable to the project.
|
No. |
Technical Parameter |
Information to Provide |
Why It Matters |
|---|---|---|---|
|
1 |
Process Application |
Refinery, petrochemical or other process service |
Defines operating requirements |
|
2 |
Required Heat Duty |
Normal, minimum and maximum duty, kW or MW |
Determines thermal capacity |
|
3 |
Process Fluid Composition |
Fluid components and relevant properties |
Supports thermal and material design |
|
4 |
Process Flow Rate |
Minimum, normal and maximum flow rates |
Determines coil sizing and operating range |
|
5 |
Inlet Temperature |
Normal and relevant design conditions, °C |
Establishes heating requirements |
|
6 |
Outlet Temperature |
Required process outlet temperature, °C |
Defines the heating target |
|
7 |
Operating and Design Pressure |
Pressure conditions and design basis |
Supports mechanical design |
|
8 |
Allowable Pressure Drop |
Maximum permitted process-side pressure loss |
Supports hydraulic design |
|
9 |
Fuel Specifications |
Fuel type, composition, heating value and supply conditions |
Supports burner selection |
|
10 |
Furnace Configuration |
Vertical cylindrical, box-type or performance-based selection |
Affects equipment arrangement |
|
11 |
Tube Material Requirements |
Material specifications and corrosion considerations |
Supports tube integrity |
|
12 |
Combustion and Emissions Requirements |
Burner turndown, emissions limits and site requirements |
Defines combustion-system scope |
|
13 |
Site and Installation Conditions |
Ambient conditions, plot space and installation constraints |
Affects mechanical layout |
|
14 |
Codes, Inspection and Documentation |
Applicable standards, inspection plan and deliverables |
Defines compliance requirements |
|
15 |
Delivery and Scope of Supply |
Equipment boundaries, accessories, schedule and delivery terms |
Prevents commercial omissions |
The 15 items above form a practical starting point. Depending on the application, a manufacturer may require additional data before completing detailed engineering.



3. How to Prepare Each Technical Requirement Correctly
3.1 Process Application and Operating Conditions
Start by identifying the intended process service.
Common fired heater applications include crude oil heating, vacuum distillation feed heating, hydroprocessing feed heating, and other refinery or petrochemical process heating duties.
The manufacturer needs to understand how the heater will operate, including startup, normal production, reduced throughput, and relevant design conditions.
A furnace designed for one process fluid should not automatically be assumed suitable for another.
3.2 Required Heat Duty
Heat duty is one of the most important RFQ parameters.
It represents the useful thermal energy that must be transferred to the process fluid.
For a simplified single-phase heating case:

For streams involving vaporization, chemical reactions, or significant property changes, the heat duty should be determined using an appropriate enthalpy balance.
Buyers should specify the required duty and operating cases instead of asking the supplier to determine capacity from the equipment dimensions alone.
3.3 Process Fluid Composition and Flow Rate
Process fluid properties influence heat transfer, pressure drop, tube-metal temperature, and material selection.
For hydrocarbon services, the supplier may need information about viscosity, density, heat capacity, thermal conductivity, vaporization behavior, and thermal stability.
The RFQ should also identify the expected minimum and maximum flow rates.
This is particularly important because inadequate process flow can reduce tube cooling and increase overheating risk.
3.4 Inlet and Outlet Temperatures
Specify the required process inlet and outlet temperatures for each relevant operating case.
A single outlet temperature is not enough to define the heater's thermal behavior.
For example, changes in inlet temperature or process throughput can significantly alter the required firing rate and tube-temperature distribution.
3.5 Operating Pressure and Allowable Pressure Drop
The process pressure and allowable pressure drop affect coil configuration, tube dimensions, hydraulic performance, and mechanical design.
Both operating and design pressures should be clearly identified.
For high-pressure applications, the equipment design may require additional mechanical and material considerations.
3.6 Fuel Specifications
A fired heater manufacturer needs accurate fuel information to evaluate the combustion system.
Typical information includes fuel type, composition, heating value, supply pressure, supply temperature, and relevant operating variations.
If the project requires dual-fuel operation, this should be stated explicitly.
Different fuel characteristics can affect burner selection, combustion performance, and emissions.
3.7 Furnace Configuration
Some EPC projects specify a particular furnace configuration based on the plant layout or existing equipment.
Others allow the manufacturer to propose a suitable arrangement.
Common options include:
Vertical cylindrical fired heaters
Box-type fired heaters
Specialized process furnace configurations
When the furnace type is not fixed, the RFQ should identify the technical and site constraints that will determine the selection.
3.8 Tube Materials and Design Requirements
Process tube materials must be suitable for the design temperature, pressure, fluid characteristics, and expected damage mechanisms.
Material selection should consider potential corrosion, oxidation, creep, and other service-specific degradation risks.
Buyers should provide any mandatory material specifications and applicable project requirements.
3.9 Combustion and Emissions Requirements
The RFQ should specify the applicable emissions requirements, fuel conditions, operating range, and combustion-control expectations.
Burner performance should be evaluated as part of the overall heater design.
The project may also require particular instrumentation, protective systems, and combustion-safety functions.
3.10 Site Conditions and Equipment Layout
Site conditions can influence the furnace structure, materials, installation method, and delivery arrangement.
Important information may include ambient temperature, elevation, wind and seismic requirements, available plot space, access restrictions, and lifting limitations.
For international EPC projects, transportation dimensions and site assembly requirements may also be important.
3.11 Codes, Inspection and Documentation
The RFQ should identify the governing codes and project specifications.
API Standard 560 is commonly referenced for direct-fired heaters in general refinery service. Other applicable requirements may address mechanical design, tubes, burners, instrumentation, inspection, and project documentation.
Buyers should specify required inspections, testing, material records, and documentation deliverables.
3.12 Delivery and Scope of Supply
A clear scope of supply is essential for comparing quotations.
The RFQ should state whether the supplier's scope includes burners, coils, refractory, structures, instrumentation, control equipment, accessories, transportation, and site services.
Responsibilities for engineering interfaces and installation support should also be defined.
4. Five Common Fired Heater RFQ Mistakes That Increase Project Costs
Even experienced industrial buyers can encounter procurement problems when important requirements are missing.
Mistake 1: Requesting a Price Based Only on Heat Duty
A statement such as "We need a 15 MW fired heater" does not provide enough information for a reliable technical quotation.
The manufacturer still needs process conditions, fuel data, pressure requirements, and project specifications.
Better approach: Provide a complete process design basis and identify any information that remains preliminary.
Mistake 2: Ignoring Minimum Operating Flow
A furnace may perform adequately at its normal design point but experience different thermal conditions at reduced throughput.
Better approach: Include minimum and maximum operating cases and require the supplier to identify relevant operating limitations.
Mistake 3: Comparing Quotations with Different Supply Scopes
One supplier may include burners, instruments, refractory, and technical documentation, while another may quote only the main furnace assembly.
Better approach: Use a common scope-of-supply checklist and request a clear list of exclusions.
Mistake 4: Overlooking Inspection and Documentation Requirements
Missing inspection requirements can create additional costs and schedule problems later in the project.
Better approach: Specify the required quality documentation and inspection expectations before contract award.
Mistake 5: Choosing the Lowest Price Without Reviewing Lifecycle Cost
A lower initial quotation may not provide the best long-term value.
Fuel consumption, maintenance accessibility, equipment reliability, and inspection requirements can affect total ownership cost.
Better approach: Compare technically compliant proposals using both capital and operating cost considerations.
5. How to Compare Fired Heater Quotations from Different Manufacturers
A quotation comparison should evaluate more than the total price.
|
Evaluation Criteria |
What Buyers Should Verify |
|---|---|
|
Thermal Performance |
Required heat duty and operating cases |
|
Process Conditions |
Flow, temperature, pressure and pressure drop |
|
Tube Design |
Material, tube-metal temperature and design basis |
|
Combustion System |
Fuel compatibility, burner scope and operating range |
|
Energy Performance |
Efficiency definition and fuel consumption assumptions |
|
Inspection |
Testing, inspection plan and documentation |
|
Scope of Supply |
Included equipment, accessories and exclusions |
|
Delivery Schedule |
Manufacturing milestones and delivery terms |
|
Technical Support |
Engineering coordination and site support scope |
|
Commercial Terms |
Payment terms, warranty and contractual responsibilities |
If suppliers use different assumptions, request technical clarification before comparing prices.
For critical equipment, technical compliance should be established before commercial ranking.
6. What Determines Fired Heater Price?
The fired heater price depends on the equipment's design requirements and scope of supply.
A customized refinery fired heater cannot be priced reliably from heating capacity alone.
Major cost drivers include:
Heat duty and equipment dimensions: Higher thermal requirements may require larger coils, structures, and associated systems.
Operating temperature and pressure: Demanding process conditions can influence materials, tube thickness, and mechanical design.
Tube material: Material grade and quantity can significantly affect equipment cost.
Burner and combustion systems: Fuel requirements, operating range, emissions, and controls influence combustion-system complexity.
Inspection and documentation: Project-specific inspection, testing, and documentation requirements affect manufacturing and delivery costs.
Transportation and installation: Shipping dimensions, modularization, site restrictions, and installation responsibilities may influence total project expenditure.
Example: Why Similar Heat Duty Does Not Mean Similar Price
Consider two hypothetical fired heater projects.
|
Parameter |
Project A |
Project B |
|---|---|---|
|
Required Heat Duty |
12 MW |
12 MW |
|
Process Fluid |
Relatively clean service |
Fouling-sensitive hydrocarbon service |
|
Design Temperature |
Moderate |
Higher |
|
Tube Material |
Standard specified alloy |
Higher-grade alloy required |
|
Fuel System |
Single fuel |
Dual fuel |
|
Inspection Scope |
Standard project requirements |
Additional project-specific requirements |
|
Expected Cost Complexity |
Lower |
Higher |
These are illustrative scenarios, not actual Chunlei quotations.
Although both projects require the same heat duty, their technical specifications and equipment costs may differ significantly.
For an accurate quotation, buyers should submit their process data and project requirements to a qualified fired heater supplier.
7. How to Evaluate a Fired Heater Manufacturer for an EPC Project
Choosing a reliable fired heater manufacturer requires assessing engineering capability, manufacturing quality, project coordination, and technical documentation.
Engineering and Customization
A suitable manufacturer should be able to review the process design basis and explain how the proposed furnace configuration meets the project requirements.
For custom equipment, engineering coordination is especially important when the project involves unusual operating conditions or existing plant interfaces.
Manufacturing and Quality Control
Buyers should review the proposed manufacturing quality plan, material documentation, inspection requirements, and testing procedures.
The level of inspection should match the project specifications and applicable requirements.
Technical Documentation
Confirm which documents will be supplied and when they will be issued.
Typical deliverables may include equipment data sheets, general arrangement drawings, material documentation, inspection records, and other agreed technical documents.
Project Coordination
For international projects, communication between the manufacturer, EPC contractor, and end user is essential.
Important topics include technical clarification, drawing approval, delivery milestones, inspection coordination, and installation interfaces.
After-Sales and Technical Support
Buyers should confirm the available technical support and the exact responsibilities included in the contract.
Support arrangements should be agreed before equipment delivery rather than assumed.
8. Why Consider Chunlei Chemical Machinery for Custom Fired Heaters?
Chunlei Chemical Machinery provides industrial process equipment solutions for chemical, petrochemical, and refinery-related projects.
For customers seeking a custom fired heater manufacturer or supplier, the starting point is a clear understanding of the required process conditions and equipment scope.
Chunlei Chemical Machinery can discuss project requirements such as:
Required heating capacity and operating range
Process fluid and temperature conditions
Furnace configuration and installation constraints
Tube materials and mechanical requirements
Fuel and combustion-system specifications
Manufacturing and inspection requirements
Project documentation and delivery coordination
For EPC contractors, early technical communication can help clarify equipment interfaces, procurement responsibilities, and design assumptions.
The final technical proposal, manufacturing scope, performance requirements, and inspection deliverables should be confirmed through approved project documents.
Looking for a Fired Heater Factory or Manufacturer?
If your project requires a new refinery fired heater, petrochemical process heater, or customized industrial furnace, prepare your technical specifications and request a quotation based on the actual process requirements.
Contact Chunlei Chemical Machinery to discuss your fired heater project and request a technical proposal.


9. Frequently Asked Questions About Fired Heater RFQs
1: What is the most important information in a fired heater RFQ?
The process design basis is essential. It should include heat duty, fluid properties, flow rates, temperatures, pressures, fuel specifications, and relevant operating conditions.
2: Can I request a fired heater quotation without complete engineering data?
You can request a preliminary discussion or budgetary estimate, but the manufacturer may need to make assumptions. A firm technical and commercial quotation generally requires more complete information.
3: Why do fired heater prices vary between suppliers?
Prices may differ because of design assumptions, materials, burner systems, inspection requirements, documentation, equipment scope, and commercial terms.
4: Should I specify a vertical cylindrical or box-type fired heater?
Specify the configuration when it is required by the process design or project layout. Otherwise, the supplier may be able to propose a suitable arrangement based on the technical requirements.
5: What standards should be included in a fired heater RFQ?
API 560 is commonly relevant for direct-fired heaters in general refinery service. Other standards and project specifications may apply depending on the equipment, location, and scope.
6: How can EPC buyers compare quotations fairly?
Use a common technical specification, compare supplier assumptions, identify deviations, and confirm that the equipment scopes and performance requirements are equivalent.
7: Can a fired heater manufacturer provide customized equipment?
Customized equipment may be developed based on process conditions, fuel requirements, site constraints, and applicable engineering specifications. The available engineering and manufacturing scope should be confirmed with the supplier.
8: What should I check before choosing a fired heater factory?
Review engineering capability, manufacturing quality, inspection requirements, technical documentation, project coordination, and the proposed scope of supply.
9: Does a higher thermal efficiency always mean a better fired heater?
Not necessarily. Efficiency should be considered alongside process performance, equipment reliability, emissions, maintenance, and total lifecycle cost.
10: What is the best way to get an accurate fired heater price?
Provide a complete RFQ with process conditions, equipment specifications, applicable standards, and scope-of-supply requirements. This helps the manufacturer prepare a technically meaningful quotation.